Timeline for Service Delivery, Directorate of Boilers (GoWB)
Sl. No. | Services | Designated Officer | Stipulated Time Limit | Appellate Officer | Reviewing Officer | ||
---|---|---|---|---|---|---|---|
Designation | Stipulated Time Limit | Designation | Stipulated Time Limit | ||||
1. | Issuance of provisional order of Boiler under Form V / Economiser under Form X (Registration and Renewal). | Assistant Director of Boilers/Deputy Director of Boilers as applicable. | 15days after satisfactory inspection | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
2. | Issuance of Final Certificate of Boiler under Form VI / Economiser under Form XI (Registration and Renewal). | Assistant Director of Boilers/Deputy Director of Boilers as applicable. | 6 months after satisfactory inspection | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
3. | Examination of Boiler/Economiser under Registration. | Assistant Director of Boilers/Deputy Director of Boilers as applicable. | 30days from the date of receipt of the application for Registration | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
4. | Inspection of Boiler/Economiser for renewal of certificates. | Assistant Director of Boilers/Deputy Director of Boilers as applicable. | 15days from the date of receipt of the application. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
5. | Issuance of Certificate of Boilers, Economiser, their components, etc. during manufacturing. | Assistant Director of Boilers/Dy.Director of Boilers as applicable. | 30days after submission of complete authentic documents and fees. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
6. | Examination and approval of Drawings. | Assistant Director of Boilers/Dy.Director of Boilers as applicable. | 45days after submission of complete authentic drawings, documents and fees. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
7. | Change of Ownership of Boilers/Economiser. | Assistant Director of Boilers/Dy.Director of Boilers as applicable. | 60days after submission of complete authentic documents and fees. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
8. | Approval of Repairer/Erector/Manufacturer of Boiler and Pipe Line and Renewal thereof/Endorsement of Repairer/Erector of Boiler and Pipe Line. | Assistant Director of Boilers/Dy.Director of Boilers as applicable. | 30days after submission of complete authentic documents and fees. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
9. | Registration Of Steam and Feed Pipe Lines. | Assistant Director of Boilers/Dy.Director of Boilers as applicable. | 30days after submission of complete authentic documents and fees. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
10. | Testing of Materials at Testing Laboratory. | Inspecting Officer/Superintendent of testing laboratory. | 7days after completion of testing. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
11. | Issuance of Erection Certificate of Boilers/Economiser. | Assistant Director of Boilers/Dy.Director of Boilers as applicable. | 30days after completion of hydraulic test of Boilers/Economiser. | Joint Director of Boilers | 45Days | Director of Boilers | 60Days |
Click HERE to view / download the timeline for the delivery of different services of Directorate of Boilers (GoWB)
Click HERE to view / download the COMPREHENSIVE INSPECTION POLICY and Report Submission Timeline