Timeline for Service Delivery, Directorate of Boilers GoWB

Timeline for Service Delivery, Directorate of Boilers (GoWB)

Sl. No. Services Designated Officer Stipulated Time Limit Appellate Officer Reviewing Officer
Designation Stipulated Time Limit Designation Stipulated Time Limit
1. Issuance of provisional order of Boiler under Form V / Economiser under Form X (Registration and Renewal). Assistant Director of Boilers/Deputy Director of Boilers as applicable. 15days after satisfactory inspection Joint Director of Boilers 45Days Director of Boilers 60Days
2. Issuance of Final Certificate of Boiler under Form VI / Economiser under Form XI (Registration and Renewal). Assistant Director of Boilers/Deputy Director of Boilers as applicable. 6 months after satisfactory inspection Joint Director of Boilers 45Days Director of Boilers 60Days
3. Examination of Boiler/Economiser under Registration. Assistant Director of Boilers/Deputy Director of Boilers as applicable. 30days from the date of receipt of the application for Registration Joint Director of Boilers 45Days Director of Boilers 60Days
4. Inspection of Boiler/Economiser for renewal of certificates. Assistant Director of Boilers/Deputy Director of Boilers as applicable. 15days from the date of receipt of the application. Joint Director of Boilers 45Days Director of Boilers 60Days
5. Issuance of Certificate of Boilers, Economiser, their components, etc. during manufacturing. Assistant Director of Boilers/Dy.Director of Boilers as applicable. 30days after submission of complete authentic documents and fees. Joint Director of Boilers 45Days Director of Boilers 60Days
6. Examination and approval of Drawings. Assistant Director of Boilers/Dy.Director of Boilers as applicable. 45days after submission of complete authentic drawings, documents and fees. Joint Director of Boilers 45Days Director of Boilers 60Days
7. Change of Ownership of Boilers/Economiser. Assistant Director of Boilers/Dy.Director of Boilers as applicable. 60days after submission of complete authentic documents and fees. Joint Director of Boilers 45Days Director of Boilers 60Days
8. Approval of Repairer/Erector/Manufacturer of Boiler and Pipe Line and Renewal thereof/Endorsement of Repairer/Erector of Boiler and Pipe Line. Assistant Director of Boilers/Dy.Director of Boilers as applicable. 30days after submission of complete authentic documents and fees. Joint Director of Boilers 45Days Director of Boilers 60Days
9. Registration Of Steam and Feed Pipe Lines. Assistant Director of Boilers/Dy.Director of Boilers as applicable. 30days after submission of complete authentic documents and fees. Joint Director of Boilers 45Days Director of Boilers 60Days
10. Testing of Materials at Testing Laboratory. Inspecting Officer/Superintendent of testing laboratory. 7days after completion of testing. Joint Director of Boilers 45Days Director of Boilers 60Days
11. Issuance of Erection Certificate of Boilers/Economiser. Assistant Director of Boilers/Dy.Director of Boilers as applicable. 30days after completion of hydraulic test of Boilers/Economiser. Joint Director of Boilers 45Days Director of Boilers 60Days

Click HERE to view / download the timeline for the delivery of different services of Directorate of Boilers (GoWB)
Click HERE to view / download the COMPREHENSIVE INSPECTION POLICY and Report Submission Timeline